Survey necessary to bridge the gap between paper documents and ground reality, Calcutta High Court directs completion of trial in 6 months
Justice Uday Kumar in his order dated 28 August rejected the lower court's decision dated 1 February 2025, ...
Explanation in simple terms
- What:
- The court ordered a land survey to compare official property documents with the actual layout of the land.
- Who:
- Justice Uday Kumar is the judge who issued the order regarding a property encroachment dispute.
- When:
- The order was dated 28 August and reported on 1 Sep 2026.
- Where:
- The case is at the Calcutta High Court in West Bengal.
- Why:
- The court decided that a survey is needed to resolve differences between written records and the physical land.
- What it means:
- The court canceled a previous lower court decision and required the trial to finish within six months.